Table 1.2-1 Summary of Resource Impacts/Avoidance and Minimization Measures

Impact Type

Project Plan Sheet

Wetlands

Waters of the US

Avoidance & Minimization Measures
Comments

Environmental Protection Measures

Proposed Pole

Existing Pole

Perm. (SF)

Temp. (SF)

System

Perm. (SF)

Temp. (SF)

Stream Crossing

System

WSSC

Area (SF)

Length (LF)

NEW STR 3

312

2

38

3,752

Church WET1

0

0

0.0

0.0


Avoidance has been evaluated but because of engineering constraints it is not feasible at this location. Increasing span length would result in taller and additional structures. Adjusting east or west would result in a larger foundation with greater disturbance adjacent to the wetland. Work area in wetland is required for access and removal of existing structure.

Matting, E&SC BMP

NEW STR 10

319

5

0

40

Church WET2

0

0

0.0

0.0


Structure relocated out of buffer, no permanent impact to wetland or buffer. No Access is proposed from north between Str. 9 and 10 through wetland minimizing temporary impacts. Temporary impact can't be reduced further because of access to existing pole.

Matting, E&SC BMP

NEW STR 18

327

9

0

2,500

Sudlersville WET1

0

0

0.0

0.0


Angle structure relocated out of wetland, No Access is proposed from south between Str. 18 and 19 through Wetland/Stream minimizing temporary impacts. Temporary impact can't be reduced because of access to existing pole.

Matting, E&SC BMP

NEW STR 22

331

11

0

0


0

0

0.0

0.0


Stream Crossing is avoided because no access is proposed between Str. 22 and 23 to avoid Stream Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 23

332

11

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 25

334

12

0

0


0

0

0.0

0.0


Stream Crossing is avoided because no access is proposed between Structures 25 and 26 to avoid Stream Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 26

335

13

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 30

339

15

0

0


0

0

0.0

0.0


Stream Crossing is avoided because no access is proposed between Structures 30 and 31 to avoid Stream Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 31

340

15

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 32

341

16

0

0


0

0

0.0

0.0


Impacts have been minimized through the use of the existing culvert to cross Stream between Str. 32 and 33.

E&SC BMP

NEW STR 33

342

16

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 34

343

17

0

0


0

0

0.0

0.0


No Access between Str. 34 and 35 to avoid Stream Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 35

344

17

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 36

345

18

0

0


0

0

0.0

0.0


The work area adjusted to avoid temporary Wetland impacts.

Matting, E&SC BMP

NEW STR 39

348

19

0

0


0

0

0.0

0.0


No Access between Str. 39 and 40 to avoid Stream Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 40

349

20

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 41

350

20

0

0


0

0

0.0

0.0


No Access between Str. 41 and 423 to avoid Stream Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 42

351

21

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 43

352

21

0

730

Duhamel WET1

0

0

0.0

0.0


Construction constraints (Pulling site) limit ability to reduce temporary impacts to wetlands.

Matting, E&SC BMP

NEW STR 44

353

22

0

2

Duhamel WET3

0

0

0.0

0.0


Structure relocated out of buffer avoiding permanent impacts; utilize existing farm road/culvert to access.

Matting, E&SC BMP

NEW STR 45

354

22

38

3,754

Duhamel WET5

0

0

0.0

0.0


Avoidance has been evaluated but because of engineering constraints it is not feasible at this location. Increasing span length would result in taller and additional structures. Work area in wetland is required for access and removal of existing structure. The access road has been located to minimize temporary wetland impacts.

E&SC BMP

NEW STR 46

355

23

0

0


0

0

0.0

0.0


No Access between Str. 46 and 47 to avoid Stream Crossing minimizing temporary impacts.

Matting, E&SC BMP

NEW STR 47

356

23

63

3,351

Duhamel WET6

0

0

0.0

0.0


The Angle structure has been relocated closer to edge of wetland. Further avoidance has been evaluated but because of engineering constraints it is not feasible at this location. Increasing span length would result in taller and additional structures. Work area in wetland is required for access and removal of existing structure.

Matting, E&SC BMP

NEW STR 48

357

24

0

793

Duhamel WET7

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact.

Matting, E&SC BMP

NEW STR 49

358

24

0

10,602

Duhamel WET7, Duhamel WET9

0

0

0.0

0.0


Construction constraints (Pulling site) limit ability to reduce temporary impacts to wetlands.

Matting, E&SC BMP

NEW STR 51

360

25

38

5,009

Basic WET2

0

0

0.0

0.0


Avoidance has been evaluated but because of engineering constraints it is not feasible at this location. Increasing span length would result in taller and additional structures. Work area in wetland is required for access and removal of existing structure. The access road has been located to minimize temporary wetland impacts.

Matting, E&SC BMP

NEW STR 52

361

26

38

5,009

Basic WET2

0

0

0.0

0.0


Avoidance has been evaluated but because of engineering constraints it is not feasible at this location. Increasing span length would result in taller and additional structures. Work area in wetland is required for access and removal of existing structure.

Matting, E&SC BMP

NEW STR 53

362

26, 27

38

5,009

Basic WET2

0

0

0.0

0.0


No Access between Str. 53 and 54 to avoid Wetland Crossing minimizing temporary impacts.

Matting, E&SC BMP

NEW STR 54

363

27

38

5,009

Basic WET2

0

0

0.0

0.0


Matting, E&SC BMP

NEW STR 55

364

27, 28

0

1,081

Basic WET3

0

0

0.0

0.0


No Access between Str. 55 and 56 to avoid Wetland Crossing minimizing temporary impacts. Construction constraints (Pulling site) limit ability to reduce temporary impacts to wetlands.

Matting, E&SC BMP

NEW STR 56

365

28

2

1,109

Barclay WET1

0

0

0.0

0.0


Matting, E&SC BMP

NEW STR 57

366

29

0

3,176

Barclay WET2

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact, access through wetland minimized.

Matting, E&SC BMP

NEW STR 58

367

29

0

2,504

Barclay WET2

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact, access through wetland minimized.

Matting, E&SC BMP

NEW STR 59

368

29, 30

0

2,871

Barclay WET3

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact, access through wetland minimized.

Matting, E&SC BMP

NEW STR 60

369

30

0

3,213

Barclay WET3

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact, access through wetland minimized.

Matting, E&SC BMP

NEW STR 61

370

30, 31

0

0


0

0

0.0

0.0


Temporary impacts have been minimized by utilizing the existing farm road/culvert to access.

Matting, E&SC BMP

NEW STR 62

371

31

0

253

Woodyard WET2

0

0

0.0

0.0


Engineering constraints (span lengths) required pole to be relocated within buffer.

Matting, E&SC BMP

NEW STR 64

373

32

0

20,191

Woodyard WET3, Woodyard WET4

0

0

0.0

0.0


Structure relocated out of buffer. Utilize existing culvert to access.

Matting, E&SC BMP

NEW STR 65

374

32

0

0


0

0

0.0

0.0


No Access between Str. 64 and 65 to avoid Wetland Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 66

375

33

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 68

377

34

0

0


0

0

0.0

0.0


Temporary impacts have been minimized by utilizing the existing farm road/culvert to access.

Matting, E&SC BMP

NEW STR 70

379

35

0

1,156

Zion WET1

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact. No Access between Str. 70 and 71 to avoid Wetland Crossing minimizing temporary impacts.

Matting, E&SC BMP

NEW STR 71

380

36

0

0


0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact. No Access between Str. 71 and 72 to avoid Wetland Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 72

381

36

0

0


0

18

165.3

15.0

Zion WUS1

The work area has been minimized to avoid the stream channel.

Temp Stream Crossing, E&SC BMP

NEW STR 74

383

37

0

0


0

0

0.0

0.0


Temporary impacts to wetlands have been minimized by utilizing the existing culvert for access to Str. 74. Structure 75 has been relocated out of wetland avoiding permanent impact. No Access between Str. 74 and 75 to avoid Wetland Crossing minimizing temporary impacts.

Matting, E&SC BMP

NEW STR 75

384

38

0

2,503

Schults WET2

0

0

0.0

0.0


Matting, E&SC BMP

NEW STR 76

385

38

0

820

Schults WET2

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact.

Matting, E&SC BMP

NEW STR 77

386

39

0

0


0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact, access through wetland minimized. Further avoidance has been evaluated but because of engineering constraints it is not feasible at this location. Increasing span length would result in taller and additional structures. Work area in wetland is required for access and removal of existing structure.

Matting, E&SC BMP

NEW STR 78

387

39

0

2,721

Trunk WET1

0

0

0.0

0.0


Construction constraints (Pulling site) limit ability to reduce temporary impacts to wetlands.

Matting, E&SC BMP

NEW STR 82

391

41

0

0


0

0

0.0

0.0


Temporary impacts to wetlands have been minimized by utilizing the existing culvert for access.

Matting, E&SC BMP

NEW STR 83

392

41, 42

0

557

Trunk WET4

0

0

0.0

0.0


Access through wetland minimized.

Matting, E&SC BMP

NEW STR 87

396

43

0

552

Bee WET1

0

0

0.0

0.0


Construction constraints (Pulling site) limit ability to reduce temporary impacts to wetlands.

Matting, E&SC BMP

NEW STR 88

397

44

0

1,009

Bee WET1

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact, access through wetland minimized.

Matting, E&SC BMP

NEW STR 90

399

45

0

3,429

Bee WET1

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact, access through wetland minimized.

Matting, E&SC BMP

NEW STR 91

400

45

63

2,273

Bee WET1

0

0

0.0

0.0


Avoidance has been evaluated but because of engineering constraints it is not feasible at this location. Increasing span length would result in taller and additional structures.

Matting, E&SC BMP

NEW STR 92

401

46

0

3,005

Bee WET5

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact, access through wetland minimized.

Matting, E&SC BMP

NEW STR 93

402

46

0

24

Bee WET7

0

0

0.0

0.0


Avoidance has been evaluated but because of engineering constraints it is not feasible at this location. Increasing span length would result in taller and additional structures. Work area in wetland minimized.

Matting, E&SC BMP

NEW STR 94

403

47

0

0


0

0

0.0

0.0


No Access between Str. 94 and 95 to avoid Wetland Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 95

404

47

0

4,496

Bee WET7

0

0

0.0

0.0


Matting, E&SC BMP

NEW STR 97

406

48

0

0


0

0

0.0

0.0


No Access between Str. 97 and 98 to avoid Wetland Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 98

407

49

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 99

408

49

0

4,885

Henderson WET4

0

0

0.0

0.0


Construction constraints (Pulling site) limit ability to reduce temporary impacts to wetlands.

E&SC BMP

NEW STR 100

409

50

63

5,003

Henderson WET4

0

0

0.0

0.0


Avoidance has been evaluated but because of engineering constraints it is not feasible at this location. Increasing span length would result in taller and additional structures. Work area in wetland is required for access and removal of existing structure.

Matting, E&SC BMP

NEW STR 101

410

50

38

3,759

Henderson WET4

0

0

0.0

0.0


Avoidance has been evaluated but because of engineering constraints it is not feasible at this location. Increasing span length would result in taller and additional structures. Work area in wetland is required for access and removal of existing structure. Access road located to minimize wetland crossing.

Matting, E&SC BMP

NEW STR 102

411

51

38

3,759

Henderson WET4

0

0

0.0

0.0


Avoidance has been evaluated but because of engineering constraints it is not feasible at this location. Increasing span length would result in taller and additional structures. Work area in wetland is required for access and removal of existing structure. Access road located to minimize wetland crossing.

Matting, E&SC BMP

NEW STR 103

412

51

0

82

Henderson WET4

0

0

0.0

0.0


Work area in wetland buffer is required for access and removal of existing structure. Access road located to minimize wetland crossing.

Matting, E&SC BMP

NEW STR 105

414

52

0

464

Henderson WET5

0

0

0.0

0.0


Work area in wetland buffer is required for access and removal of existing structure. Access road located to minimize wetland crossing.

Matting, E&SC BMP

NEW STR 106

415

52

0

622

Henderson WET6

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact. Further avoidance has been evaluated but because of engineering constraints it is not feasible at this location. Increasing span length would result in taller and additional structures. Work area in wetland is required for access and removal of existing structure.

Matting, E&SC BMP

NEW STR 109

418

54

0

2,977

Henderson WET7

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact. Construction constraints (Pulling site) limit ability to reduce temporary impacts to wetlands.

Matting, E&SC BMP

NEW STR 110

419

54

0

2,406

Sandtown WET2

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact. No Access between Str. 109 and 110 to avoid Stream Crossing minimizing temporary impacts.

Matting, E&SC BMP

NEW STR 111

420

55

0

0


0

0

0.0

0.0


Temporary impacts have been minimized by utilizing the existing farm road for access

E&SC BMP

NEW STR 112

421

55

0

24,473

Sandtown WET3

0

0

0.0

0.0


Temporary impacts have been minimized by utilizing the existing farm road for access.

E&SC BMP

NEW STR 113

422

55, 56

0

0


0

0

0.0

0.0


Temporary impacts have been minimized by utilizing the existing farm road for access.

E&SC BMP

NEW STR 114

423

56

0

0


0

0

0.0

0.0


Temporary impacts have been minimized by utilizing the existing farm road for access.

E&SC BMP

NEW STR 115

424

56

0

0


0

0

0.0

0.0


Temporary impacts have been minimized by utilizing the existing farm road for access.

E&SC BMP

NEW STR 116

425

57

0

0


0

0

0.0

0.0


No Access between Str. 116 and 117 to avoid Stream Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 117

426

57

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 119

428

58

0

0


0

0

78.4

15.0

Broadway WUS1

Stream crossing is required between Str. 119 and 120.

Temp Stream Crossing, E&SC BMP

NEW STR 120

429

59

0

0


0

0

NEW STR 121

430

59

0

36

Broadway WET2

0

0

0.0

0.0


The work area adjusted to minimize wetland impact.

Matting, E&SC BMP

NEW STR 123

432

60

0

0


0

0

0.0

0.0


Work area adjusted to minimize wetland impact, No Access between Str. 123 and 124 to avoid Wetland Crossing minimizing temporary impacts.

Matting, E&SC BMP

NEW STR 124

433

61

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 127

436

62

0

0


0

0

0.0

0.0


Access adjusted to minimize wetland impacts.

Matting, E&SC BMP

NEW STR 128

437

63

0

0


0

0

0.0

0.0


Work area adjusted to minimize wetland impact, No Access between Str. 128 and 129 to avoid Wetland Crossing minimizing temporary impacts.

Matting, E&SC BMP

NEW STR 129

438

63

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 130

439

63, 64

0

0


0

0

6.4

5.0

Red Bridges WUS1

Temporary impacts have been minimized by utilizing the existing farm road/culvert to access Str. 131. There will be no impacts to stream during construction. No access between structures 131 and 132 to avoid wetland/stream crossing minimizing temporary impacts.

Matting, E&SC BMP

NEW STR 131

440

64

0

0


0

0

Matting, E&SC BMP

NEW STR 132

441

64

0

0


0

0

0.0

0.0


Matting, E&SC BMP

NEW STR 134

443

65

0

0


0

0

40.0

5.0

Red Bridges WUS7

Temporary impacts have been minimized by utilizing the existing farm road/culvert to access There will be no impacts to stream during construction.

Matting, E&SC BMP

NEW STR 135

443A

66

0

0


0

0

99.9

15.0

Red Bridges WUS3

Temporary impacts have been minimized by utilizing the existing farm road/culvert to access.

Temp. Stream crossing, Matting, E&SC BMP

NEW STR 136

444

66

0

0


0

0

85.1

15.0

Red Bridges WUS6

Stream crossing is required between Str. 136 and 137.

Temp. Stream crossing, Matting, E&SC BMP

NEW STR 137

445

67

0

0


0

0

NEW STR 138

446

67

0

0


0

0

0.0

0.0


No Access between Str. 138 and 139 to avoid Wetland/Stream Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 139

447

68

0

6

Stallings WET2

0

0

0.0

0.0


Structure has been relocated out of wetland buffer avoiding permanent impact.

Matting, E&SC BMP

NEW STR 145

453

71

0

0


0

0

0.0

0.0


No Access between Str. 145 and 146 to avoid Stream Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 146

454

71

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 150

458

73

0

0


0

0

0.0

0.0


No Access between Str. 150 and 151 to avoid Stream Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 151

459

74

0

3,468

Whiteleysburg WET1

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact.

Matting, E&SC BMP

NEW STR 157

465

76

0

0


0

0

0.0

0.0


No Access between Str. 157 and 158 to avoid Stream Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 158

466

77

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 165

473

80

0

0


0

0

0.0

0.0


Temporary impacts have been minimized by utilizing the existing farm road/culvert to access.

E&SC BMP

NEW STR 166

474

81

0

319

Kibler WET1

0

0

0.0

0.0


No Access between Str. 166 and 167 to avoid Wetland/Stream Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 167

475

81

0

2,729

Kibler WET1

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact.

Matting, E&SC BMP

NEW STR 170

478

83

0

0


0

0

0.0

0.0


No Access between Str. 170 and 171 to avoid Stream Crossing minimizing temporary impacts.

E&SC BMP

NEW STR 171

479

83

0

0


0

0

0.0

0.0


Structure has been relocated out of wetland buffer avoiding permanent impact. No Access between Str. 171 and 172 to avoid Stream Crossing minimizing temporary impacts.

Matting, E&SC BMP

NEW STR 172

480

84

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 174

482

85

0

0


0

0

0.0

0.0


No Access between Str. 174 and 175 to avoid Stream Crossing minimizing temporary impacts. The work area has been adjusted to avoid stream impacts.

E&SC BMP

NEW STR 175

483

85

0

0


0

0

0.0

0.0


E&SC BMP

NEW STR 177

485

86

0

1,660

Burrsville WET1

0

0

0.0

0.0


Structure has been relocated out of wetland avoiding permanent impact.

Matting, E&SC BMP

NEW STR 180

488

88

95

111,459

Burrsville WET2

0

0

0.0

0.0


Multiple new structures are required for the installation of the switches for the Oil City Tap. Significant work areas/access for all of the construction activities in this area for the Oil City Tap. for structure placement.

Matting, E&SC BMP

NEW STR 181

488B

88

38

0

0

0.0

0.0


Matting, E&SC BMP

NEW STR 182

488C

88

38

0

0

0.0

0.0


Matting, E&SC BMP

NEW STR 183

488D

88

38

0

0

0.0

0.0


NEW STR 184

489

88

28

0

0

0.0

0.0


NEW STR 185

490

89

0

530

Burrsville WET4

0

0

0.0

0.0


Structure has been relocated into the wetland buffer. Further avoidance has been evaluated but because of engineering constraints it is not feasible at this location. Increasing span length would result in taller and additional structures.

Matting, E&SC BMP

Structure Total Impacts

737

271,141


0

18



1 WUS System

Access Road Impacts

0

121,652

35 Wetland Systems

0


475


6 WUS Systems

Totals

737

392,793


0

18

475

70